Put a working bank reconciliation behind every ERP payment, or pay Birmingham's bill

Birmingham's £128.1M Oracle bill is six times the 2019 estimate. Buyers who pay ERP suppliers on dates and effort, not on tests against their own live data, are funding the failure.

Birmingham City Council went live with its new Oracle finance, HR and payroll system in April 2022 with a red warning on file. Officials had been warned, in red, that the system might pay people late, let debts go uncollected and misstate the accounts. They approved go-live anyway. The combined cost of that launch and this year's rebuild is now £128.1M, against £19.96M in the 2019 business case. At one point the funding allocation reached £157M.

I expected to write about a vendor that sold a council something it could not deliver. The published facts do not support that. The council planned to run Oracle out of the box, then built customisations, including a bank reconciliation system that did not work. It could not understand its cash position or produce auditable accounts, and it has spent more than £5M on manual workaround labour, so most of the failure sits with the council.

I still think the fix is in the contract, and I think the missing piece is a payment gate that the buyer's own finance function controls. Officials can read a red warning and still approve a programme that has already slipped. The project was meant to go live in April 2021 and went a year late. By then every official in the chain had a career reason to say yes. Holding back an invoice attaches a cost to the same warning. If the final tranche is due only when the system closes a month of real books on live data, the go-live decision is made by a test result. The people who want to ship have to explain why they are paying for something that failed.

I do not know what Birmingham's contract said. The Audit Committee papers I have seen do not tell me whether Oracle or its implementation partner had payment milestones, or how much of the £128.1M went to suppliers. That is the first thing I would ask for. If payment followed dates and effort, every month of slippage was revenue for somebody, and the council was paying for the supplier's learning curve in real time. If it followed acceptance tests, I want to know who signed them off.

The obvious objection is that gates would not have stopped either failure. A buyer determined to customise will customise, and a buyer that ignores a red warning will ignore a red gate. I agree that a gate the buyer can waive quietly is worth nothing. So write the waiver into the contract as a priced variation that goes to the audit committee, or the equivalent board, in writing. Officials can still choose to go live over a failed reconciliation, but they do it on paper, with the cost attached and a name beside it. Birmingham's officials made that choice with nothing to show for it except a warning now quoted in a national trade paper.

Suppliers will push back, and that is useful. They will ask for higher rates, a smaller retention or narrower acceptance criteria. Each of those is the supplier telling you what it thinks the risk is worth, which is information a buyer never gets from a fixed-date plan. If a supplier will not accept a gate on the one thing that decides whether you can pay staff and collect tax, I would want to know before signing.

Private buyers should not feel safe because this is a council. Summaries of a 2024 Gartner forecast say more than 70% of recently implemented ERP initiatives will miss their original business case goals by 2027, and as many as 25% will fail catastrophically. I have not seen the Gartner original, so treat the figures as secondhand. Even so, a plan that assumes success is the unusual plan.

The damage also goes well beyond the invoice. The 2019 business case booked £27M of savings from 2019 to 2031. The Audit Reform Lab at the University of Sheffield estimated in 2024 that lost savings and deteriorating tax collection would take the total impact to £216.5M by April 2026. None of that shows up as a line on a supplier's invoice, so none of it can be recovered through a retention you never wrote.

Open your largest live software contract this week and find the final payment. If it falls due on a date rather than after a reconciliation, payroll run or invoice cycle on your own data, you hold the same kind of contract Birmingham may have signed, and you should change it at the next change order.

Prompted by Bill for Birmingham's Oracle debacle reaches £128M, theregister.